Caltrans Says Bolt Problem On New Bay Bridge Permanently Fixed

OAKLAND (CBS SF) — Workers have finished a permanent fix for problem bolts on the new eastern span of the Bay Bridge, a Caltrans spokesman said Wednesday.

Spokesman Andrew Gordon said the work was completed around 11 a.m. Wednesday and cost about $25 million, which is about twice the amount that transportation officials predicted when the bolt problem was discovered in the spring.

Gordon said the cost was higher than originally expected because, “This was a unique, complex problem that demanded a unique, complex solution.”

In March, nearly one-third of the 96 bolts that secure earthquake shock absorbers known as shear keys to the deck of the bridge failed when they were tightened.

The shear keys are designed to prevent swaying during an earthquake, which is a key element in the construction of the $6.4 billion span because the goal is to make it seismically safe since a portion of the existing bridge failed in the 1989 Loma Prieta earthquake.

The problem threatened to delay the plan by transportation officials to open the new eastern span, which is intended to be safer in earthquakes than the old span, over Labor Day weekend.

But transportation officials then learned of and approved a short-term fix which involved inserting large steel plates, known as shims, into each of four bearings, enhancing their ability to safely distribute energy during an earthquake.

The long-term solution to fixing the broken bolts on the eastern span was to cover them with an exterior saddle and cable system that is encased in concrete.

Gordon said the temporary shims were removed Wednesday.

Several engineering experts have expressed concern that there could be problems over the long term with other bolts on the new eastern span but Gordon said tests are being conducted to address those concerns and see if those bolts must be replaced at some point.

He said those tests are expected to be completed by next fall.

But Gordon said Caltrans officials believe that the new eastern span is safe.

(Copyright 2013 by CBS San Francisco and Bay City News Service. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.)

  • State Senate Report: Caltrans Allowed Bad Welds On New Bay Bridge « CBS San Francisco

    […] Dozens of the bolts ended up snapping after being tightened in March, leading to a $25 million repair job. […]

  • Phil Matier: Bay Bridge Contractor Receives Millions In Bonuses « CBS San Francisco

    […] (KCBS) – Despite plenty of problems, from broken bolts to water leaks, the main contractor on the new Bay Bridge has received nearly $49 million in […]

  • List: The New Bay Bridge’s Biggest Problems « CBS San Francisco

    […] new eastern span of the San Francisco-Oakland Bay Bridge has had its share of recent woes since the controversy over the flawed bolts discovered during the final stages of construction, with the most recent being the discovery […]

blog comments powered by Disqus
Guide To The Holidays
Shine A Light On The Holiday Season With ‘Giving Tuesday’

Listen Live